3 floors · 40,000 sq ft · built 1927 · class K2 · owner of record: Mz Roosevelt Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 4 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 70 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 70 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 40,000 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 191 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 191 days | Annual filing |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Oct 15, 2025 | Construction CLASS - 2 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR AMENDMENTS : SWS NOT CONFORMING TO PLAN #Q01252410-P1 THAT THE SWS IS TO COVER THE FULL WIDTH OF THE BUILDING PLUS ADDITIONAL 5 FT ON EACH END OF #39163649Y | Jul 13, 2026 IN VIOLATION | $625 |
| Oct 15, 2025 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPARTMENT OF BUILDINGS NOTED VIOLATION #39148188P AND #39138508X ISSUED FOR FTM BUILDING EXTERIOR WALL AT TIME OF IN #39163650L | Jun 15, 2026 IN VIOLATION | $625 |
| Aug 12, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN A CODE COMPLIANT MANNER NOTED: AT TIME OF INSPECTION OBSERVED DEFECTIVE /MISSING MORTAR WITH VISIBLE CRACKS BETWEEN BRICK WALL, BUILDING FACADE EXP#3 (41ST AVENUE), REPAIR AND/OR #39156758H | Oct 21, 2025 DEFAULT | $5,000 |
| May 16, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN A CODE COMPLIANT MANNER NOTED: AT TIME OF INSPECTION OBSERVED BROKEN/DEFECTIVE/MISSING MORTAR WITH VISIBLE CRACKS BETWEEN BRICKS AT BUILDING REAR FACADE AND PARAPET WALL ON (41ST #39148188P | Jun 15, 2026 IN VIOLATION | $3,125 |
| Dec 9, 2022 | Construction CLASS - 1 FAILURE TO PROVIDE ADEQUATE ROOT PROTECTION. AT TIME OF INSPECTION I OBSERVED A SUPPORTED SF INSTALLED AT EXP#2 ON THE ADJOINING PROPERTY ROOF. THE RESPONDENT FAILED TO PROVIDE A ROOF PROTECTION MEETING THE REQ #39510216M | Feb 22, 2024 IN VIOLATION | $625 |
| Dec 9, 2022 | Construction CLASS - 1 AT TIME OF INSPECTION, I OBSERVED 4 WORKERS WORKING ON A SUPPORTED SCAFFOLD INSTALLED AT EXPOSURE 2, SCAFFOLD IS NOT MAINTAINED AS REQUIRED, MISSING GUARDRAILS, NETTING NOT MAINTAINED AND LOOSE PLANKS. THESE CO #39510217Y | Feb 22, 2024 IN VIOLATION | $2,500 |
| Sep 15, 2022 | Construction CLASS - 1 AT TIME OF MY INSPECTION OBSERVED FACADE REPAIR WORKING ACTIVITY WITHOUT A PERMIT AS REQUIRED. THE BUILDING EXPOSURE 2 ALL EXTERIOR 5 INCH BRICK DEMOLISHED AND REST OF WALL UNSAFE CONDITION. UPON REQUEST ANY DO #39506349Y | Jan 7, 2025 IN VIOLATION | $2,500 |
| Sep 15, 2022 | Construction CLASS - 1 FAILURE TO PROVIDE LICENSE TO ENTER ADJOINING PROPERTY.. I OBSERVED SUPPORTED PIPE SCAFFOLD INSTALLED EXPOSURE 2 ONE STORY BUILDING ON ROOF UP TO 3RD FLOOR LEVEL ABOUT 24 FEET. UPON REQUEST FOR LICENSE TO ENTE #39506362Z | Jun 4, 2024 IN VIOLATION | $2,500 |
| Sep 15, 2022 | Construction CLASS - 1 FAILURE TO PROVIDE ADEQUATE ROOF PROTECTION. I OBSERVED SUPPORTED PIPE SCAFFOLD INSTALLED EXPOSURE 2 ONE STORY BUILDING ON ROOF ABOUT 24 FEET HEIGHT WITH DID NOT PROVIDE ADJOINING ROOF PROTECTION SHALL CONSIST #39506356M | Jan 7, 2025 IN VIOLATION | $2,500 |
| Sep 15, 2022 | Construction CLASS - 1 AT TIME OF MY INSPECTION OBSERVED SUPPORTED PIPE SCAFFOLD INSTALLED EXPOSURE 2 ONE STORY BUILDING ON ROOF UP TO 3RD FLOOR LEVEL ABOUT 24 FEET WITH NOT MAINTAIN AS REQUIRED. THE SCAFFOLD MISSING GUARDRAILS, NETT #39506355K | Jan 7, 2025 IN VIOLATION | $2,500 |
| Aug 16, 2014 | Construction CLASS - 2 ALT/CHANGED BLDG OCCUPIED W/O A VALID C OF O.NOTED TEMP C OF O #401723033T008 ISSUED 12/21/09 EXP 2/21/10.REM:OBTAIN VALID C OF O OR DISCONTINUE ILLEGAL OCCUP. #35026085L | Feb 3, 2015 IN VIOLATION | $0 |
| Aug 16, 2014 | Construction CLASS - 2 OCCUPANCY CONTRARY TO THAT ALLOWED BY THE C OF O OR BLDG DEPT RECORDS.NOTED DOB & C OF O #401723033T008 RECORDS STATES CELLAR(BOILER/STORAGE),BALCONY(MOTION P.C.THEATRE)1ST FL(RETAIL/SUPER MARKET),2ND FL(CLOTHI #35026086N | Feb 3, 2015 IN VIOLATION | $0 |
| Jul 29, 2005 | Construction Non-Hazardous ALTERED BUILDING OCCUPIED WITHOUT A VALID CERTIFICATE OF OCCUPANCY. NOTED: TEMPORARY CERTIFICATE OF OCCUPANCY 401723033 EXPIRED 07/28/05. REMEDY: OBTAIN VALID CERTIFICATE OF OCCUPANCY OR DISCONTINUE USE. #34488503P | Oct 16, 2007 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Sep 26, 2022 | CONSTRUCTION #E40401MM | DOB VIOLATION - ACTIVE |
| Oct 10, 2019 | ELEVATOR #9028/664284 | DOB VIOLATION - ACTIVE |
| Aug 2, 2019 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #01772 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 4) | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Aug 2, 2019 | Benchmarking - LL84 FTF-EN-BENCH | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)