1 floors · 15,500 sq ft · built 1929 · class G1 · owner of record: Nyc Department Of Sanitation
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 44 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2023-12-14 (Accepted). Agency page | Dec 31, 2026 in 44 days | 1 of 1 without an accepted 2026 report yet |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 3 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 775 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| May 22, 2019 | Unknown CLASS - 1 TEMPORARY POWER INSTALLED WITHOUT A PERMIT., OBTAIN PERMIT #39003286L | May 29, 2019 POP/IN-VIO | $0 |
| May 22, 2019 | Construction CLASS - 1 TEMPORARY FUEL STORAGE TANK INSTALLED WITHOUT A PERMIT., OBTAIN PERMIT #39003269J | May 29, 2019 POP/IN-VIO | $0 |
| Jun 18, 2018 | Boilers CLASS - 2 36)AS PER DOB RECORDS, BOILER IS NOT REGISTERED WITH THIS DEPT. #32096972M | Oct 19, 2018 POP/IN-VIO | $0 |
| Jun 18, 2018 | Construction CLASS - 1 B101,50. 50-FOUND NO PERMITS TO INSTALL BOILER AT SITE AS PER DOB RECORDS. BURNHAM MODEL #V910A BTU 1578 MBH. #32096971K | Nov 2, 2018 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #06346 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #25243 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #05467 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #05436 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION #26929 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #09863 | DOB VIOLATION - ACTIVE |
| Sep 23, 2021 | CONSTRUCTION EMERGENCY WORK ORDER-MASONRY WALLS AND WOOD FRAMED ROOF DETACHED VACANT BLDG IN SEVERE STATE OF DISREPAIR. ONE BOWSTRING TRUSS COLLAPSE ON 6/19. THE ROOF HAS FURTHER COLLASPED. THE REMAINDER OF THE ROOF FRAMING(BOWSTRING TRUSSES)IS IN STATE OF DISREPAIR AND THERE IS POTEN OF FURTHER COLLASPE. REMEDY #FEU20301XC | DOB VIOLATION - ACTIVE |
| Jun 24, 2020 | CONSTRUCTION FAILURE TO COMPLY W/COMM'S ORDER#315795 07/01/19 TO FILE FOR PERMIT BY 08/01/2019 AND START WORK BY 09/01/2019-MAKE BLDG CODE COMPLIANT AS OF 06/24/2020.BLDG HAS NOT BEEN REPAIRED OR DEMOLISHED.NO JOBS FILED FOR PERMIT WITH THE DEPARTMENT.IMMEDIATELY COMPLY WITH COMMISSIONER'S ORDR # 315795 #FEU20301XC | DOB VIOLATION - ACTIVE |
| Jul 29, 2019 | CONSTRUCTION EMERGENCY WORK ORDER:1 STRY DETACH MASN WALLS&WOOD TRUSS FRAMED ROOF (BOW STRING TRUSSES)ON 6/28/19 ONE TRUSS OF ROOF COLLAP.THE ROOF PART COLLAP APPX 50'WIDE SECTION.THE EXT WALLS ARE NOT BRACED AND THERE IS POSSIBILITY OF COLLAP.IMMED BRACE WALL ALONG WEST FARM ROAD UND DIRECT AND CONTINOUS SUPERV #FEU20301XC | DOB VIOLATION - ACTIVE |
| Jul 1, 2019 | CONSTRUCTION FTM:TRUSS ROOF,APPROX 150'W BY 110'D IN DISREP.ONE ROOF TRUSS COLLAP CAUSING A 50' WIDE SECT OF ROOF TO PART COLLAP&HANG FROM OTHERTRUSSES FRNT WALL IS PART UNBRACED.DETERIOR&CRACKED BRICKS NOTED ON ALL WALLS FULLY VACATE BLDG. OWNER ENGAGE PE EVALUATE STRUCTURE&MAKE BLDG CODE OMPLIANT UNDER PRMT. F #FEU20301XC | DOB VIOLATION - ACTIVE |
| Jun 28, 2019 | CONSTRUCTION EMERG WRK ORDER: ONE ROOF TRUSS COLLAP BY EXP4 & REMAINDER OF TRUSS IS RESTING ON EXP3 WALL.ROOF SUPPORTED ON THIS TRUSS HAS PART COLLAP AREA (50'WX100'D +/-),LEAVING PERIMETER WALLS IMPROPERLY BRACED. OWNR IMMED ENGAGE PE&ENDORSED CONTR ERECT T/B/F ALONG WEST FARM ROAD TO PROTECT THE PUBLIC.WRK DON #FEU20301XC | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 3) | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 17, 2026, 8:17 PM ET. BBL 2030150049.