2 floors · 6,950 sq ft · built 1931 · class M1 · owner of record: Congregation & Yeshiva Tifereth Yisroel Moishe
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 66 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (3 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-12-01 (Accepted). Agency page | Dec 31, 2026 in 66 days | 3 of 3 without an accepted 2026 report yet |
| Gas piping inspection (2027 cycle) Likely applies Local Law 152 · During 2027 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 12 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2027 in 431 days | Next cycle year 2027 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 2, 2009 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPARTMENT OF BUILDINGS. RESPONDENT FAILED TO COMPLY WITH THE COMMISSIONER'S ORDER TO CORRECT THE VIOLATIONS AND FILE #34804383L | Feb 22, 2010 WRITTEN OFF | $0 |
| Mar 14, 2009 | Construction CLASS - 1 SEC.28-201.1 FAILURE TO COMPLY WITH COMMISSIONERS ORDER TO CORRECT VIO 34687469M FOR WORK W/O A PERMIT SPRINKLER SYSTEM HAS BEEN INSTALLED W/O A PERMIT REMEDY: COMPLY WITH ORDER #34772484R | May 4, 2009 WRITTEN OFF | $0 |
| Aug 28, 2008 | Construction CLASS - 1 WORK W/O PERMITS. NOTED: INSTALLATION OF SPRINKLER SYSTEM AT REAR BUILDING SECTION W/O REQUIRED D.O.B. PERMITS. REMEDY: OBTAIN REQUIRED D.O.B.. PERMITS. REMEDY: REMEDY: OBTAIN REQUIRED D.O.B. PERMITS FORTHWITH #34687469M | Oct 20, 2008 WRITTEN OFF | $0 |
| Aug 28, 2008 | Construction CLASS - 2 OCCUPANCY CONTRARY TO THAT ALLOWED BY C/O NOTED: AT REAR BUILDING SECTION,1ST FLR & BASEMENT OCCUPIED AS A DAY CARE CONTRARY TO C/O #217181 THAT STATES SYNAGOGUES,STUDY/PLAYER ROOMS. NOTED: NO STATE CERTIFICATE #34687470J | Aug 17, 2009 WRITTEN OFF | $0 |
| Issued | Violation | Status |
|---|---|---|
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #21868 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #19356 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #19357 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #39740 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #39742 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #39741 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #23756 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #21181 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #21182 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #13873 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #13872 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #13871 | DOB VIOLATION - ACTIVE |
| Apr 5, 2019 | PRIVATE RESIDENTIAL ELEVATOR 2017 VIOS ISSUED TO ELEVATORS IN PRIVATE RES DWELLINGS (1 OR 2 FAMILY DWELLINGS) #00438 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 2, 2026 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2025 Cat1 Test Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2024 Cat1 Test Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2023 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2021 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2018 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2022 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
| Apr 5, 2019 | Elevators JVIOS | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Report | Open |