| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 67 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 65,880 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 188 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 188 days | Annual filing |
| Energy audit and retro-commissioning (2028) Likely applies Local Law 87 · Calendar year 2028 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 8188). Agency page | Dec 31, 2028 in 798 days | Next due 2028 |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 18 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1163 days | Next cycle year 2029 |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-01-15 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Mar 4, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. USE OF PROHIBITED DOOR AND/OR HARDWARE PER BC 1008.1.8; 27-371(J). AT THE TIME OF INSPECTION, THE FOLLOWING ROOM DOORS HAD TURN KNOBS HARDWARE:-329, 328, 3 #35722294R | Apr 10, 2026 POP/IN-VIO | $0 |
| Mar 4, 2026 | Construction CLASS - 2 RE-ISSUED 35691723R. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. ILLUMINATION FOR EXITS, EXIT DISCHARGES AND PUBLIC CORRIDORS PERBC 1006.1; 27-381. AT THE TIME OF INSPECTION, ONE EMERGENCY LIGHT IN C #35722292N | Apr 2, 2026 POP/IN-VIO | $0 |
| Mar 4, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NO FIRE STOPPING PER BC 712.3; 27-345. AT THE TIME OF INSPECTION MULTIPLE PENETRATIONS WERE OBSERVED IN THE ELECTRICAL METER ROOM, HENCE THE ROOM WAS NOT F #35722295Z | Apr 2, 2026 POP/IN-VIO | $0 |
| Mar 4, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING WALL(S) OR APPURTENANCES. AT THE TIME OF INSPECTION, AN OBSOLETE SECURITY CAMERA MOUNTED ON THE EXTERIOR WALL APPEARS AS IF IT COULD FALL ANY TIME BECAUSE THE METAL BRACKET CONNECTI #35722296K | Apr 2, 2026 POP/IN-VIO | $0 |
| Mar 4, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION THE FOLLOWING ROOM DOORS WERE NOT SELF-CLOSING:-329, 317, 231, 117. STAIR "D" AND "C" ON 3RD FLOOR WERE NOT SELF-CLOSING PROPERLY #35722293P | Apr 2, 2026 POP/IN-VIO | $0 |
| Mar 17, 2025 | Construction CLASS - 2 RE-ISSUE #35677267L. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: ILLUMINATION FOR EXITS, EXIT DISCHARGES AND PUBLIC CORRIDORS PERBC 1006.1; 27-381. NOTED: IN THE CORRIDOR NEXT TO THE AUDITORIUM THREE #35691723R | Apr 16, 2025 POP/IN-VIO | $0 |
| Apr 25, 2024 | Construction CLASS - 2 REISSUED#35672085H FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.ILLUMINATION FOR EXITS,EXIT DISCHARGES AND PUBLIC CORRIDOR PER BC 1006.1;27-381.EMERGENCY EXISTING LIGHT ARE NOT OPERATIONAL WEN TESTED C #35677267L | Jul 24, 2024 POP/IN-VIO | $0 |
| Feb 23, 2023 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.ILLUMINATION FOR EXITS, EXIT DISCHARGES & PUBLIC CORRIDORS PER BC 1006.1; 27-381.NOTED:AT GYMNASIUM EM #11, CAFETERIA EM #2, & CORRIDOR EM #4 BY ROOM 103 EM #35672085H | Jun 7, 2023 POP/IN-VIO | $0 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
None open.