3 floors · 155,720 sq ft · built 1960 · class W1 · owner of record: Nyc Department Of Education
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 61 days | Keep the report on file (not filed with DOB) |
| Energy audit and retro-commissioning (2026) Likely applies Local Law 87 · Calendar year 2026 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 8496). Agency page | Dec 31, 2026 in 61 days | Due this year |
| Annual boiler inspection (4 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-01-14 (Accepted). Agency page | Dec 31, 2026 in 61 days | 1 of 4 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 155,720 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 182 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 182 days | Annual filing |
| Gas piping inspection (2027 cycle) Likely applies Local Law 152 · During 2027 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 15 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2027 in 426 days | Next cycle year 2027 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| May 1, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. USE OF PROHIBITED DOOR AND/OR HARDWARE PER BC 1008.1.8; 27-371(J). AT THE TIME OF INSPECTION, THE FOLLOWING DOORS HAD TURN KNOB HANDLES:-306, 309, 311, 313 #35732963Y | May 27, 2026 POP/IN-VIO | $0 |
| May 1, 2026 | Construction CLASS - 2 RE-ISSUE 35721270H. AT THE TIME OF INSPECTION, THE DOORS WERE NOT SELF-CLOSING:-302, 305, 303A, 309, CORRIDOR DOOR NEXT TO 308, 311, 310, 313, STAIRCASE "D" ON 3RD FLOOR, 315, 320, 319, 327, 317, 329, 332, 338, #35732962M | May 27, 2026 POP/IN-VIO | $0 |
| May 1, 2026 | Construction CLASS - 2 RE-ISSUE 35721269K. AT THE TIME OF INSPECTION, THE OIL TANK ROOM HAD ACRACK IN CONCRETE WALL THAT HAD WATER TRICKLING DOWN. REMEDY: REPAIR AND/OR REPLACE. #35732967L | May 27, 2026 POP/IN-VIO | $0 |
| May 1, 2026 | Construction CLASS - 2 RE-ISSUE 35721268Z. AT THE TIME OF INSPECTION, THE GAS AND ELECTRICAL METER ROOMS HAD CEILING/WALL PENETRATIONS, GAS AND ELECTRICAL METER ROOMS ARE NOT FIRE-STOPPED. REMEDY: PROVIDE/MAINTAIN FIRE STOPPING. #35732965H | May 27, 2026 POP/IN-VIO | $0 |
| May 1, 2026 | Construction CLASS - 2 RE-ISSUE 35721272L. AT THE TIME OF INSPECTION, BULKHEAD "C" WALL HAS SPALLED, HOWEVER THE REPAIRED AREAS HAD BUBBLING. THE SAME WALL LOCATION ON 3RD FLOOR HAD BUBBLING. REMEDY: REPAIR AND/OR REPLACE. #35732966J | May 27, 2026 POP/IN-VIO | $0 |
| May 1, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. ILLUMINATION FOR EXITS, EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1; 27-381. AT THE TIME OF INSPECTION, THE FOLLOWING EMERGENCY LIGHTS WERE INOPERAB #35732964X | May 27, 2026 POP/IN-VIO | $0 |
| Jul 22, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.CRACK IN BULKHEAD AND DOWN THE STAIRS FROM WATER LEAKS COMING FROM ROOF LEVEL.REM:REPAIR AND/OR REPLACE. #35721272L | Sep 3, 2025 POP/IN-VIO | $0 |
| Jul 22, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NO FIRESTOPPING PER BC 712.3;27-345.LARGE OPEN HOLES IN ELECTRICAL AND GAS METER ROOM FIRESTOP NOT DONE.REM:PROVIDE MAINTAIN FIRESTOPPING. #35721268Z | Sep 3, 2025 POP/IN-VIO | $0 |
| Jul 22, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.OIL TANK ROOM CRACK IN WALL LEAKING AND OIL TANK SUPPORT ONE SITE HAS CRACK IN THE CONCRETE SUPPORT.REM:REPAIR AND/OR REPLACE. #35721269K | Sep 3, 2025 POP/IN-VIO | $0 |
| Jul 22, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.CLASSROOM DOOR NOT SELF CLOSING MISSING HARDWARE IN ROOM 202,205,207,209,208,211,213,217,219,249,231,232,234,229,320,317,313,310,311,309,308,305.REM:REPAIR #35721270H | Sep 3, 2025 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #03554 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |